Extension of the 400 kV Gura Ialomitei GIS Substation 

Client: C.N.T.E.E.  Transelectrica S.A.
Contractor: C.N.T.E.E.  Transelectrica S.A. – S.T. Bucharest


Extension of the 400 kV Gura Ialomitei substation with two OHL 400 kV bays Cernavoda and Stalpu.

Scope of works

  • Extension of the 400 kV substation with two new GIS bays.

Our role

  • Design of the 400 kV substation extension
    • Fesability Study
    • Tender Specifications.